RENCANA ANGGARAN BIAYA (RAB) |
|||||||||
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
TAHUN ANGGARAN 2020 | |||||||||
Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
Sub Bidang | : | Pekerjaan Umum dan Penataan Ruang (2.3.) | |||||||
Kegiatan | : | Pembangunan Jembatan Milik Desa (2.3.13.) | |||||||
Jembatan Kayu Lantai Beton RT. 1 RW. 2 Dusun Bahagia ukuran 3 m x 7 m | |||||||||
Waktu Pelaksanaan | : | 30 (tiga puluh hari kalender) | |||||||
Rincian Pendanaan | : | ||||||||
NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
1 | 2 | 3 | 4 | 5 | |||||
I. | BAHAN | (harga utk contoh saja) | |||||||
1. | Kayu Belian uk. 10/10 cm - 3 M | 16.00 | Btg | 370,000.00 | 5,920,000.00 | ||||
2. | Kayu Belian uk. 9/9 cm -3 M | 10.00 | Btg | 300,000.00 | 3,000,000.00 | ||||
3. | Kayu Belian uk. 9/9 cm - 4 M | 14.00 | Btg | 350,000.00 | 4,900,000.00 | ||||
4. | Kayu Belian uk. 8/8 cm - 3 M | 24.00 | Btg | 250,000.00 | 6,000,000.00 | ||||
5. | Kayu Belian uk. 4/8 cm - 4 M | 4.00 | Btg | 150,000.00 | 600,000.00 | ||||
6. | Papan Belian uk. 2/15 cm - 4 M | 38.00 | Kpg | 120,000.00 | 4,560,000.00 | ||||
7. | Baut uk. 5/8" | 136.00 | Btg | 11,000.00 | 1,496,000.00 | ||||
8. | Plat Beugel | 24.00 | Bh | 56,000.00 | 1,344,000.00 | ||||
9. | Semen Portland | 40.00 | Zak | 95,000.00 | 3,800,000.00 | ||||
10. | Pasir beton | 3.00 | M3 | 90,000.00 | 270,000.00 | ||||
11. | Batu Pecah uk. 1-2 cm | 4.00 | M3 | 400,000.00 | 1,600,000.00 | ||||
12. | Besi beton polos ø 8 mm | 44.00 | Btg | 85,000.00 | 3,740,000.00 | ||||
13. | Besi beton polos ø 10 mm | 46.00 | Btg | 100,000.00 | 4,600,000.00 | ||||
14. | Pipa GIF ø 2" - 6 M tebal 3 mm | 5.00 | Btg | 600,000.00 | 3,000,000.00 | ||||
15. | Kawat beton | 8.00 | Kg | 26,000.00 | 208,000.00 | ||||
16. | Kayu klas II 3/5 - 4 M | 30.00 | Btg | 19,000.00 | 570,000.00 | ||||
17. | Papan Kayu mal 1.5/12 - 4 M | 90.00 | Kpg | 19,000.00 | 1,710,000.00 | ||||
18. | Kayu cerucuk dia 8-10/4m | 50.00 | Btg | 8,000.00 | 400,000.00 | ||||
19. | Paku Belian u/ shear conector | 5.00 | Kg | 28,000.00 | 140,000.00 | ||||
20. | Paku Belian | 5.00 | Kg | 28,000.00 | 140,000.00 | ||||
21. | Paku campur | 13.00 | Kg | 19,000.00 | 247,000.00 | ||||
22. | Cat Minyak @1 kg | 2.00 | Klg | 60,000.00 | 120,000.00 | ||||
23. | Timbunan oprit | 4.00 | M3 | 100,000.00 | 400,000.00 | ||||
Jumlah Bahan | 48,765,000.00 | ||||||||
II. | SEWA ALAT (sesuai keperluan) | ||||||||
1. | Gerobak Dorong | 2.00 | Bh | 200,000.00 | 400,000.00 | ||||
2. | Concrete mixer (molen) & op. | 2.00 | hari | 200,000.00 | 400,000.00 | ||||
Jumlah Alat | 800,000.00 | ||||||||
III. | UPAH | ||||||||
1. | Pekerja | 64.00 | HOK | 85,000.00 | 5,440,000.00 | ||||
2. | Tukang | 51.00 | HOK | 120,000.00 | 6,120,000.00 | ||||
3. | Kepala Tukang | 5.00 | HOK | 140,000.00 | 700,000.00 | ||||
4. | Mandor | 3.00 | HOK | 120,000.00 | 360,000.00 | ||||
123.00 | HOK | Jumlah Upah | 12,620,000.00 | ||||||
IV. | HONOR TPK | ||||||||
1. | Ketua | 1.00 | org | 450,000.00 | 450,000.00 | ||||
2. | Sekretaris | 1.00 | org | 400,000.00 | 400,000.00 | ||||
3. | Anggota | 3.00 | org | 350,000.00 | 1,050,000.00 | ||||
(Perbup Sanggau No. 1 Thn. 2019) | |||||||||
5.00 | org | Jumlah Honor TPK | 1,900,000.00 | ||||||
J U M L A H (Rp.) | 64,085,000.00 |
Sabtu, 12 Oktober 2019
Desain dan RAB Jembatan Kayu Lantai Beton
Langganan:
Posting Komentar (Atom)
BalasHapusBoleh minta RAB dan Desainnya pak? Jika boleh, ini email saya pak : willyland46@gmail.com.
Sebelumnya Terima Kasih dan Mohon Maaf pak.
Boleh minta RAB nya pak untuk jalan gang tempat saya secara swadaya..mohon bantuannya 🙏
BalasHapusBisa minta ilmu analisa kebutuhan barang pembuatan jembatan Ulin ini?
BalasHapusBisa minta analisis supaya bisa hitungkan kebutuhan?
BalasHapusBoleh minta analisanya pak terimakasih
BalasHapusAssalamualaikum pak
BalasHapusijin, apa boleh share analisanya pak, sebagai acuan sesuai kebutuhan
ini email saya pak afrihadiyatullah@gmail.com, terimakasih pak