| RENCANA ANGGARAN BIAYA (RAB) | |||||||||
| DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT | |||||||||
| TAHUN ANGGARAN 2020 | |||||||||
| Bidang | : | Pelaksanaan Pembangunan Desa (2) | |||||||
| Sub Bidang | : | Pekerjaan Umum dan Penataan Ruang (2.3.) | |||||||
| Kegiatan | : | Pembangunan Prasarana Jalan Desa (Box Culvert) (2.3.14.) | |||||||
| Box Culvert RT. 1 RW. 2 Dusun Bahagia ukuran 4 m x 1,5 m x 1 m (Double) | |||||||||
| Waktu Pelaksanaan | : | 10 (sepuluh hari kalender) | |||||||
| Rincian Pendanaan | : | ||||||||
| NO. | U R A I A N | VOLUME | HARGA SATUAN (Rp) | JUMLAH (Rp) | |||||
| 1 | 2 | 3 | 4 | 5 | |||||
| I. | BAHAN | (Harga hanya contoh) | |||||||
| 1. | Semen (1 zak=50 kg) | 62.00 | zak | 90,000.00 | 5,580,000.00 | ||||
| 2. | Pasir Beton | 5.00 | M3 | 150,000.00 | 750,000.00 | ||||
| 3. | Pasir Urug | 2.00 | M3 | 140,000.00 | 280,000.00 | ||||
| 4. | Batu Pecah 2/3 cm | 7.00 | M3 | 500,000.00 | 3,500,000.00 | ||||
| 5. | Besi beton polos Ø10mm-12m | 16.00 | Btg | 100,000.00 | 1,600,000.00 | ||||
| 6. | Besi beton polos Ø15mm-12m | 50.00 | Btg | 200,000.00 | 10,000,000.00 | ||||
| 7. | Kawat Beton (Bendrat) | 13.00 | Kg | 20,000.00 | 260,000.00 | ||||
| 8. | Papan Mal uk. 2/18 cm- 4m | 61.00 | Kpg | 15,000.00 | 915,000.00 | ||||
| 9. | Kayu cerucuk Ø10cm - 4m | 100.00 | Btg | 11,000.00 | 1,100,000.00 | ||||
| 10. | Kayu 4/6 - 4m | 16.00 | Btg | 100,000.00 | 1,600,000.00 | ||||
| 11. | Paku Campur | 12.00 | Kg | 25,000.00 | 300,000.00 | ||||
| Jumlah Bahan | 25,885,000.00 | ||||||||
| II. | SEWA ALAT | ||||||||
| 1. | Gerobak Dorong | 2.00 | Bh | 200,000.00 | 400,000.00 | ||||
| 2. | Concrete mixer & operasional | 4.00 | hari | 300,000.00 | 1,200,000.00 | ||||
| Jumlah Alat | 1,600,000.00 | ||||||||
| III. | UPAH | ||||||||
| 1. | Pekerja | 50.00 | HOK | 85,000.00 | 4,250,000.00 | ||||
| 2. | Tukang | 19.00 | HOK | 120,000.00 | 2,280,000.00 | ||||
| 3. | Kepala Tukang | 3.00 | HOK | 140,000.00 | 420,000.00 | ||||
| 4. | Mandor | 22.00 | HOK | 120,000.00 | 2,640,000.00 | ||||
| 94.00 | HOK | Jumlah Upah | 9,590,000.00 | ||||||
| IV. | HONOR TPK | ||||||||
| 1. | Ketua | 1.00 | org | 300,000.00 | 300,000.00 | ||||
| 2. | Sekretaris | 1.00 | org | 250,000.00 | 250,000.00 | ||||
| 3. | Anggota | 2.00 | org | 200,000.00 | 400,000.00 | ||||
| (Perbup Sanggau No. 1 Thn. 2019) | |||||||||
| 4.00 | org | Jumlah Honor TPK | 950,000.00 | ||||||
| J U M L A H (Rp.) | 38,025,000.00 | ||||||||
| Pasir Bedengung, 8 Februari 2020 | |||||||||
| Disetujui : | |||||||||
| Kepala Desa Pasir Bedengung | Kasi Kesejahteraan | ||||||||
| Bunga Citra Lovestory, SH. | Ramlee | ||||||||
Baca juga: Box Culvert ukuran 4 x 1,5 x 1 m
BACA JUGA : Koefisien (Indeks) Bahan, Alat, Upah Pekerjaan Beton
BACA JUGA : Cara Menghitung Komposisi Campuran Beton K-225





sangat membantu pak, bisa minta tolong di kirim file desain sama RAB serta TOS nya pak?
BalasHapusEmail : relawanreju@gmail.com
terima kasih banyak pak atas ilmunya
Pak maaf mau minta tos box culvert doble 🙏🙏🙏
BalasHapusikemarsella@gmail.com
udah dikirim
HapusTerima kasih banyak banyak banyak pak
BalasHapussama2
HapusBisa minta rabx ga pak. Makasih sebelumx.. oiyand33@gmail.com..
BalasHapusmasih bisa kah minta filenya ini pak
BalasHapus